Allahabad High Court
PARAM JYOTI AND ANOTHERversusSTATE OF UP AND 2 OTHERS
- Decided
Holding
The court held that the petitioners must pursue their compensation claim before the District Level Committee under the 2016 Government Order, and therefore dismissed the writ petition.
Summary
The petitioners sought a writ of mandamus directing the State and two authorities to pay compensation for land allegedly encroached by the National Highway Authority of India and to restrain the release of compensation to other beneficiaries. The State counsel highlighted a Government Order dated 12‑05‑2016 that mandates claims for compensation be examined by a District Level Committee under the 2013 Land Acquisition Act. The court noted that under Articles 300A and 31A of the Constitution, land can be taken only with lawful compensation, and that the statutory mechanism must be followed. Consequently, the court dismissed the writ petition, directing the petitioners to file a fresh representation with the Committee within two weeks, and the Committee to decide the claim within twelve weeks. The order emphasizes adherence to the established administrative process for land compensation.
Issues considered
- Whether the High Court can issue a mandamus directing the State and authorities to pay compensation directly without invoking the statutory mechanism.
- Whether the petitioners must pursue their compensation claim before the District Level Committee as per the 2016 Government Order.
- Whether the court can restrain the release of compensation to other beneficiaries during the pendency of the petition.
Legislation cited
Subjects
- land acquisition
- compensation
- eminent domain
- mandamus
- writ petition
- District Level Committee
- Government Order
- Constitutional law
Judgment
HIGH COURT OF JUDICATURE AT ALLAHABAD
WRIT - C No. - 16119 of 2026
Param Jyoti And Another
.....Petitioner(s)
Versus
State Of Up And 2 Others
.....Respondent(s)
Counsel for Petitioner(s) : Nandini Mishra, Navin Singh, Ranjana
Singh
Counsel for Respondent(s) : C.S.C.
Court No. - 21
HON'BLE MAHESH CHANDRA TRIPATHI, J.
HON'BLE KUNAL RAVI SINGH, J.
1. Heard learned counsel for the petitioners, Shri Ambrish Shukla, learned
Additional Chief Standing Counsel for State-respondent and Sri Sudhir
Mishra, learned counsel appearing on behalf of respondent no. 3.
2. The instant writ petition has been preferred praying inter alia for the
following relief:
"1. Issue a writ order or direction in the Nature of mandamus
direct the respondent no. 2 and 3 to pay payment of compensation
of their land in question bearing Gata no. 1368 Ga, 1368 Chh,
and 1368 Jh (old Gata no. 757)total rakba 2 Beegha situated at
Village-Deokali, Tehsil Saidpur, District Ghazipur, which was
illegally encroached by the National Highway Authority of India
with interest without any delay in lieu of their unacquired land.
2. Issue a writ, order, or direction in the nature of mandamus
commanding and directing the respondent authority not to
release the compensation of the Gata no. 756 and 760 in favor of
the beneficiary during the pendency of the claim of the petitioner.
3. Issue a writ, order, or direction in the nature of mandamus
direct the respondents authority to take appropriate decision
upon the application of the petitioner dated 15.07.2025, with in
reasonable time-frame as may be fixed by this Hon'ble Court."
WRIC No. 16119 of 2026
2
3. At the very outset, learned Additional Chief Standing Counsel informed to
the Court that for redressal of grievance of tenure holders, claiming certain
right/title over their land, the State Government had issued detailed
Government Order dated 12.05.2016, which provides that in case the
claimant files claim supported with requisite documents, the same would be
considered by the District Level Committee for ensuring adequate
compensation in the light of Act 2013. He submits that once the efficacious
remedy is available to the petitioners, the matter should be relegated to the
District Level Committee, which may examine the claim of petitioners
within a reasonable time and submit its report to the Chairman/District
Magistrate, who may accord adequate compensation accordingly.
4. The position of law is well-established that in view of Article 300A and
31A of the Constitution of India, the owner of land can be divested only
in accordance with law after appropriately compensating, if such land is
required by the State for public purpose. Since, such power of eminent
domain is not in dispute, we need not advert the matter at this stage in
view of Government Order dated 12.05.2016.
5. Considering the facts and circumstances of the case and the relief prayed
in the instant matter, we dispose of the instant petition with liberty to the
petitioners to make fresh representation along with true attested copy of the
instant order before Committee constituted under the Government Order
dated 12.05.2016 within two weeks. In the event, such representation is
made, the District Level Committee shall consider the claim of the
petitioners and ensure that the proceeding shall be finalized expeditiously,
preferably within twelve weeks, thereafter.
(Kunal Ravi Singh,J.) (Mahesh Chandra Tripathi,J.)
May 6, 2026
Sumit S
Digitally signed by :-
SUMIT SRIVASTAVA
High Court of Judicature at Allahabad
Checking your session…