Allahabad High Court

SHIVDHANI SINGH AND ANOTHERversusSTATE OF U.P. AND 2 OTHERS

Decided

Holding

The competent authority under the National Highways Act, 1956 shall examine the rehabilitation and resettlement claims and make the award, not the Collector.

Summary

The petitioners' land was acquired by the National Highways Authority of India under the National Highways Act, 1956 and a compensation award was made, but no rehabilitation and resettlement (R&R) award was issued as required by the Second Schedule of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013. They sought a direction to the respondents to grant the R&R award. The Court examined earlier judgments (Ashok Kumar v. NHAI, Ranvir Singh v. NHAI, Rampal Singh v. NHAI) and held that, although the 2013 Act empowers the Collector to pass R&R awards, the acquisition under the NH Act remains governed by the competent authority designated under Section 3(a) of the NH Act. Consequently, the Court directed the competent authority, not the district Collector, to prepare and decide the R&R award within twelve weeks, following the procedures of Sections 34‑36 of the 2013 Act. The petition was disposed with that direction.

Issues considered

  • Whether the Collector of the district can pass the rehabilitation and resettlement award for land acquired under the National Highways Act, 1956.
  • Whether the competent authority designated under the National Highways Act, 1956 is the proper authority to examine claims and make the R&R award under the 2013 Act.
  • Whether the relief granted in earlier similar writ petitions applies to the present petition.

Legislation cited

Subjects

  • land acquisition
  • rehabilitation and resettlement
  • National Highways Act
  • RECLAIM Act 2013
  • competent authority
  • collector
  • award
  • NHAI

Judgment

         HIGH COURT OF JUDICATURE AT ALLAHABAD
                         WRIT - C No. - 39048 of 2026

Shivdhani Singh And Another
                                                               .....Petitioner(s)
                                    Versus

State Of U.P. And 2 Others
                                                             .....Respondent(s)

Counsel for Petitioner(s)             :   Vijay Babu Ray, Vikas Shukla
Counsel for Respondent(s)             :   C.S.C., Rajesh Kumar Jaiswal

Court No. - 29
                    HON'BLE SIDDHARTHA VARMA, J.
                    HON'BLE KUNAL RAVI SINGH, J.

1. Heard learned counsel for the petitioners, learned Standing Counsel for
State respondents and learned counsel for the contesting respondent.

2. The case of the petitioners is that their land was acquired by NHAI under
the provisions of National Highways Act, 1956 and an award was also made
but the rehabilitation and resettlement award has not been made as per the
Second Schedule to the Right to Fair Compensation and Transparency in
Land Acquisition, Rehabilitation and Resettlement Act, 2013 (in short "Act,
2013"). It has, therefore, been prayed that the respondents be directed to
make rehabilitation and resettlement award as per provisions of the Act,
2013.

3. Learned counsel for the petitioners submits that the claim of the
petitioners is similar to the one raised in Writ C No.2782 of 2023 (Ashok
Kumar and 8 others vs. National Highway Authority of India and 3
others), which was disposed of by this Court, by order dated 24.2.2023 in
terms of the order passed in Writ C No.21601 of 2022 (Ranvir Singh and
35 others vs. National Highway Authority of India and Competent
Authority For Land Acquisition and Others). The operative part of the
order passed in Writ C No.2782 of 2023 (Ashok Kumar and 8 others vs.
National Highway Authority of India and 3 others), dated 24.2.2023 is as
follows :-

     "9. Lastly the writ petitions have been disposed of with the following
     directions:-
                                                         WRIC No. 39048 of 2026
                                2


"For the above, without entering into the merits of the claim of the
petitioner, it is directed that the competent authority under the National
Highways Act, 1956 shall prepare a proposal for the rehabilitation and
resettlement award for affected families, within the meaning of Section
3(c) of the Act, 2013, in terms of the entitlements provided in the Second
Schedule, with the assistance of the officers of the NHAI and submit the
same before the Collector for making award in accordance with the
provisions of Section 31 of the RECTLARR Act, 2013.

For preparation of the said proposal, the competent authority shall make
necessary enquiry as per the provisions of the Sections 34, 35 and 36 of
the RECTLARR Act, 2013 as contained in Chapter V of the Act, 2013, i.e
before preparation of the rehabilitation and resettlement award, in
relation to the acquisition in question.
It goes without saying that the representatives of the National Highways
Authority and the affected tenure holders are entitled to participate in the
proceedings for preparation of the award. The claim of the petitioners
herein for the entitlements under the Second Schedule at serial no. (1) for
provision of housing unit in case of displacement; serial no. (4) choice of
annuity and employment and serial no. (10), one time resettlement
allowance, shall be specifically considered by the competent authority in
making such an award.

The entire exercise shall be completed, as expeditious as possible,
preferably, within a period of six months from the date of receipt of copy
of this order.
We may make it clear that, at this stage, no direction has been given for
providing benefits of Third Schedule as no such demand has been raised
by the petitioners herein.

In any case, while making such an award, independent consideration
shall be given to the elements of rehabilitation and resettlement
entitlements for the affected families provided in the Second Schedule,
without being influenced by any of the observations made hereinabove."

10. The petitioners herein are similarly situated and, therefore, are
entitled for the same relief.
                                                                WRIC No. 39048 of 2026
                                       3


     11. The present writ petition is, accordingly, disposed of."

4. It is submitted on behalf of the petitioners that the instant petition be also
disposed of in same terms.

5. Learned counsel for the respondents do not dispute that the claim of the
petitioners is identical, however, they submit that in the matters arising out
of acquisition made under the provisions of National Highways Act, 1956, it
is the Competent Authority notified by the Central Government, who is
competent to declare the award and not the Collector of the district
concerned and they submit that this aspect may be clarified by this Court.

6. This Court, recently, while deciding Writ C No. 13489 of 2024 (Rampal
Singh and 12 others vs National Highway Authority of India and 2
others) by order dated 24.04.2024, considered identical submission made on
behalf of N.H.A.I. and observed as under:

     "6. Section 23 read with Section 31 of the Act, 2013 empowers the
     Collector to pass rehabilitation and resettlement award for each affected
     family in terms of the entitlements provided in the second schedule. Under
     Section 3(g) of the Act, 2013 the Collector has been defined thus:-

     "(g) Collector means the Collector of a revenue district, and includes a
     Deputy Commissioner and any officer specially designated by the
     appropriate Government to perform the functions of a Collector under
     this Act;"

     7. It is evident from the definition of Collector that it includes any Officer
     specially designated by the appropriate Government to perform the
     functions of the Collector under the said Act.

     8. In NH Act, the power to declare award is conferred upon the competent
     authority under Section 3G. The competent authority has been defined
     under Section 3(a) of the Act of 1956 as follows:-

     "(a) "competent authority" means any person or authority authorised by
     the Central Government, by notification in the Official Gazette, to
     perform the functions of the competent authority for such area as may be
     specified in the notification;"
                                                                                                      WRIC No. 39048 of 2026
                                                                           4


                                              9. It is not disputed that the Central Government had issued notification
                                              on 28.08.2015 under Section 105(3) of the Act, 2013 directing that the
                                              provisions relating to the second and third schedule shall apply to all
                                              cases of land acquisitions under the enactments specified in the fourth
                                              schedule to the said Act. The effect of said notification is to extend the
                                              beneficial provisions of the Act, 2013 to the acquisitions made under the
                                              NH Act. However, the machinery provided for holding enquiry and
                                              determining compensation does not get altered. The same is still to be
                                              done in the manner and by the authority stipulated under the Statutes
                                              under which acquisition was done. We, therefore, find force in the
                                              submission of learned counsel for NHAI that in matters relating to
                                              acquisitions under NH Act, it would be the competent authority, as
                                              defined under Section 3(a) of NH Act, which would be empowered to
                                              examine the claims pertaining to rehabilitation and resettlement and
                                              make award accordingly and not the Collector of the district."

                                    7. In view of above, the instant petition stands disposed of with a direction
                                    to the Competent Authority under National Highways Act, 1956 to proceed
                                    with the exercise of examining the claims pertaining to rehabilitation and
                                    resettlement and take decision on the said aspect having regard to the
                                    provisions of Chapter V of the Act, 2013 within twelve weeks from the date
                                    of communication of the instant order.



                                                                      (Kunal Ravi Singh,J.) (Siddhartha Varma,J.)
                                    September 28, 2026
                                    Sumit S




Digitally signed by :-
SUMIT SRIVASTAVA
High Court of Judicature at Allahabad


Continue reading with your account

Sign in to read the full judgment. It’s free.

Sign in to read

Checking your session…

For a signed copy suitable for filing, refer to the court's website.